The end of October and early November saw the studio return to St. John for the final sessions of the year. As state in an earlier post, the group that made the trip in late October had the task of erecting the porch columns and installing the prefab porch roof panels, as well as completing the roof. The columns were first set and secured to the bases, and once the beams sat atop them, the process of attaching the roof sections was able to commence.
The remaining half of the studio travelled to St. John in early November and took on the task of creating and placing the interior walls. The walls were framed onsite, and once completed were placed in the proper position within the house. By the end of the build session, it is estimated that roughly 50% of the interior framing is complete with the rest hopefully being completed in the near future.
-Harley Schuster